Concrete by Hallack requested a mockup of the coating
system on how the subcontractor would prepare the floor.
The system, which included two coatings from Dex-O-Tex,
was given the go ahead.
Alth o ugh th e co n crete wa s n ew, all 12,650
s quare feet (1,175. 2 m²) of it s till needed to
b e p r e p p e d . C o n c r e t e b y H a l l a c k h i r e d a
subcontractor to create the right surface profile
for the coating system by Dex-O-Tex.
Once they were awarded the job, the crew
from Concrete by Hallack had five weeks to
complete the project. They needed to finish the
job before people from Spain arrived to use the
equipment, after all!
COATINGSPRO JULY 2016 29
Buttery Floor